Design and Construct New Water Treatment Plant and Ancillary Works – Kadjina Community

Benefit from our expertise in the planning and execution of providing maintenance & capital works in harsh and remote locations in a cost effective and time critical manner.

About Project

Contract Title New Water Treatment Plant and Ancillary Works – Kadjina Community
Client Housing Authority
Value $1.8m
Project Completed (date) October 2025
Statement of Work Design and construction of a new water treatment plant for the Kadjina Community to address elevated iron and manganese levels in the raw water supply.

  • Design, construction & commissioning of a precipitation and filtration water treatment plant to remove high dissolved soluble iron and manganese present in the community raw water supply.  Achieved with injection of liquified chlorine gas upstream of a DMI65 media filter, causing both dissolved iron and manganese ions to form an insoluble compound filtered and removed via DMI65 media.
  • Effective removal of iron and manganese in the community water supply, with plant performance evident in image 7931 capturing image of the backwash cycle discharge from the DMI65 filter into the adjacent evaporation pond.
  • Installation of water treatment infrastructure and ancillary components
  • Civil works and site preparation
  • Testing, commissioning, and stakeholder coordination
  • Delivery milestone achieved prior to the wet season

 

Our Past Projects