| Statement of Work |
Design, construction and commissioning of two new ground level water storage tanks to replace ageing infrastructure within the communities potable water supply.
- Establish temporary water supply
- Demolition of existing redundant infrastructure
- Import select fill and construction of civil foundation
- Underground pipework, conduits and ducting
- Construction of structural concrete footings
- Construction of two new 620kL steel liner ground tanks (raw and product tanks)
- Relocation of and commissioning of coarse media filters and liquified chlorine gas disinfection system
- Design & implementation of new SCADA system consolidating existing and new assets.
|